PROJECT

TIMELINE

TASK
RESPONSIBILITY
DATE
Kick off/Scheduling Meeting
Brook & HMH
November 4, 2022
SOW Contract Signed (40% Payment)
HMH
November 18, 2022
Design Development
Meeting 1 - Content Strategy & Design Review
Brook & HMH
November 16, 2022
Meeting 2 - Design Review
Brook & HMH
November 30, 2022
Meeting 3 - Structural Design Approval
Brook & HMH
December 14, 2022
Meeting 4 - Design Review
Brook & HMH
January 6, 2022
Meeting 5 - Final Design Approval
Brook & HMH
January 18, 2022
Progress Payment (40%)
HMH
December 14, 2022
Content Development
Gather Assets for Content Creation
HMH
January 23 - February 24, 2023
3 Revisions of Content Creation with Review Meetings
Brook & HMH
February 27 - March 31, 2023
Final Content Approval
HMH
March 31, 2023
Engineering & Production
Brook
December 19, 2022 - March 31, 2023
Shipping
Brook
April 3 - April 14, 2023
Installation
Brook
April 17 - April 21, 2023
Final Payment (20%)
HMH
April 21, 2023