TASK
|
RESPONSIBILITY
|
DATE
|
---|---|---|
Kick off/Scheduling Meeting
|
Brook & HMH
|
November 4, 2022
|
SOW Contract Signed (40% Payment)
|
HMH
|
November 18, 2022
|
Design Development
|
||
Meeting 1 - Content Strategy & Design Review
|
Brook & HMH
|
November 16, 2022
|
Meeting 2 - Design Review
|
Brook & HMH
|
November 30, 2022
|
Meeting 3 - Structural Design Approval
|
Brook & HMH
|
December 14, 2022
|
Meeting 4 - Design Review
|
Brook & HMH
|
January 6, 2022
|
Meeting 5 - Final Design Approval
|
Brook & HMH
|
January 18, 2022
|
Progress Payment (40%)
|
HMH
|
December 14, 2022
|
Content Development
|
||
Gather Assets for Content Creation
|
HMH
|
January 23 - February 24, 2023
|
3 Revisions of Content Creation with Review Meetings
|
Brook & HMH
|
February 27 - March 31, 2023
|
Final Content Approval
|
HMH
|
March 31, 2023
|
Engineering & Production
|
Brook
|
December 19, 2022 - March 31, 2023
|
Shipping
|
Brook
|
April 3 - April 14, 2023
|
Installation
|
Brook
|
April 17 - April 21, 2023
|
Final Payment (20%)
|
HMH
|
April 21, 2023
|